Application [ Popcard ] Commissioning Mode = On; Data Points In The "Commissioning" Operating Page - Siemens Synco ZW775 V2.0 Commissioning Instructions

Central communication unit
Table of Contents

Advertisement

Commissioning mode
Wiring test
Siemens Building Technologies
HVAC Products
4.6 Application [ Popcard ]
Commissioning mode = On
Many data points are displayed in Application [ Parameter Setting ] and [ Popcard ]
"Commissioning mode = On" as well as [ Popcard ] "Commissioning mode = Off".
Data point "Wiring test active" is the only data point for commissioning that is displayed
only in Application [ Popcard ] "Commissioning mode = On".

4.6.1 Data points in the "Commissioning" operating page

Command sequence: Commissioning > Commissioning mode
Data point
Commissioning mode
Default val:
Off
Setting val:
Off, On
Command sequence: Commissioning > Wiring test
Data point
Wiring test active
Default val:
No
Setting val:
No, Yes
Commissioning instructions OZW775 V2.01
Parameterize OZW775
Explanation, example
Setting value "Commissioning mode = On" in
Applications [ Popcard ] provides access to the
command "Wiring test".
See also Section 5.1.1 on "Commissioning
mode On/Off".
Explanation, example
Setting value "Commissioning mode = On" (see
above) and "Wiring test = Yes" allows for
checking inputs N.X1...N.X8 and N.D1...N.D8
as well as the outputs for Time switch 1...4 and
Fault relay 1...2.
See also Section 5.2 on "Wiring test".