System RSH Removal and Installation Activity
®
Use the Removal and Replacement procedures located in the ARCHITECT RSH Service
and Support Manual, Procedures section to perform the activity below.
1. R&R from c8000 System:
Begin with the PM Power OFF.
Perform the following steps:
a.
Loosen hex bolts
b.
Remove cables from right end
c.
Remove set screws from ground straps at both ends
d.
Disconnect c8000 LUI Keypad
e.
Remove closeout panel with c8000 LUI Keypad
f.
Remove RSH and place it on the floor in front of the system
g.
REINSTALL in reverse order
Use the INSTALL procedures located in the ARCHITECT RSH Service and Support
Manual, Procedures section to perform the activity below.
2. Orient and connect Cables
NOTE: The c8000 RSH Installation procedure within the Service & Support Manual
Connect RSH SIB Cables
Connect Sample Handler Motor Drive Cables
Card Cage Cable connections SCC attached
Power ON the PM
3. Perform key Procedures:
Perform in the order listed:
M&D 1119 Transport Calibration
As Needed Maintenance, M&D 1120 Sample Pipettor Calibration ONLY at the RSH
M&D 3222 RSH Bar Code Calibration
M&D 3319 Carrier Probe Alignment Test
M&D 3323 RSH Section Test (choose 2 different locations)
M&D 5501 RSH Motor Test
M&D 5506 RSH Sensor Test
END OF POWER & CIRCUIT BOARD TROUBLESHOOTING ACTIVITY
®
ARCHITECT
RSH Service Training Guide
201532-102
must be referenced to obtain information necessary to properly perform the
following procedures. The information can be located within the procedure
under the "Action" column header labelled:
MODULE 4: POWER AND CIRCUIT BOARDS
FOR INTERNAL USE ONLY
4-25

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents