Siemens RMB795B Basic Documentation page 28

Central control unit for room controllers rxb/rxl and room thermostats rdg/rdf/rdu
Hide thumbs Also See for RMB795B:
Table of Contents

Advertisement

Complete planning and
commissioning protocol
Installation
28 / 144
Siemens
Building Technologies
These are the individual steps to be followed when completing the Synco
planning and commissioning protocol "Communication" (C3127):
Step
Procedure
1
Enter general information about the plant
and the device types
2
Press button Menu > Update fields
3
Enter the device addresses of all users
4
Define the names and room numbers of all
users and room groups
5
Define the bus power supply according to
the supply concept
6
Define clock time operation
7
Enter the geographical zone address
8
Define the QAW zone (apartment)
9
Define the time switch zone
10
Define holidays / special day zones
11
Define the outside temperature zones
12
Define the refrigeration distribution zones
on the consumer side
13
Define the refrigeration distribution zones
on the generation side
14
Define the heat distribution zones on the
consumer side
15
Define the heat distribution zones on the
generation side
Observance of the points listed below contributes to trouble-free and effective
commissioning:
• Early coordination of installation of devices and KNX bus with the project leader
or installer responsible for the project
• Correct installation of the devices in accordance with the mounting instructions
• Observance of KNX bus installation instructions
• Setting a commissioning date on which the installation will be completed and all
forms of energy (electricity, heat and refrigeration) will have to be available
Central control unit RMB795B
Engineering and commissioning guidelines
TM
Notes
Fields that need not be
completed appear with
hatched lines
To be adopted from the floor
plans
While observing the floor
plans
Refer to Data Sheet N3127,
"KNX bus"
Autonomous, slave, master.
To be adopted from the floor
plans
According to the room group
assignments
According to customer needs
Ditto
According to HVAC plant
Ditto
Ditto
Ditto
Ditto
CE1P3122en
18.01.2012

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents