Siemens RMB795B Basic Documentation page 27

Central control unit for room controllers rxb/rxl and room thermostats rdg/rdf/rdu
Hide thumbs Also See for RMB795B:
Table of Contents

Advertisement

Planning 1:
Implement HVAC plant
concept
Planning 2:
Organize
communication
Engineer bus network
Siemens
Building Technologies
Steps required to implement the HVAC plant concept for the RMB795B central
control unit:
step
Procedure
1
Decide on the device types, their
number and application
2
Define device installation
3
RXB/RXL room controller and Synco
room thermostats RDG/RDF/RDU
combined into room groups
4
Enter the devices on the floor plan
Organization of communication on the KNX bus is subdivided as follows:
• Engineer bus network
• Complete the "Synco
(C3127)"
And these are the individual steps to be followed:
step
Procedure
1
Topology:
Define area, backbone and line, define the
device addresses
2
Define the type of bus power supply
3
Define the required system components
4
Check limitations
5
Design the network structure and
connection diagrams
6
Create the cable lists
7
Transfer the topology and the physical
device addresses [1...254] to the floor
plan
Central control unit RMB795B
Engineering and commissioning guidelines
TM
planning and commissioning protocol Communication
Notes
Number of RXB/RXL...,
RMB795B, QAW740, RMU7x,
RDG/RDF/RDU, etc.
RMB795B plug-in type or
detached operator unit, location
of controller
Based on the HVAC plant
concept given on the floor plans
Including addressing of the
room group and the
geographical zone address
[1...126].[1...63].
Notes
Depending on:
Number of devices, network
extension, embedding
Size, central, decentralize
Line couplers, bus power
supply, etc.
Number of bus users per
line, network extension, bus
power supply
Define cable routing and
cable lengths
CE1P3122en
27 / 144
18.01.2012

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents