Bottom Cable Routing - Huawei UPS5000-E-400 kVA User Manual

40 kva power modules
Table of Contents

Advertisement

UPS5000-E-(360 kVA-480 kVA)
User Manual (40 kVA Power Modules)
Bind signal cables and power cables separately.
Step 3 Route signal cables. Bind cables to the cabinet.
from the top of the cabinet.
Figure 3-38 Routing control cable from the top of the cabinet
----End

3.2.7.2 Bottom Cable Routing

Prerequisites
Issue 07 (2020-01-10)
The number and colors of control cables in
If you choose to route cables from the bottom of the cabinet, ensure sufficient space at the
bottom of the cabinet.
If you choose to route cables through holes, remove power cable tray covers and drill
holes. After you drill holes, paste grommet strip to the hole edge to protect cables.
Reinstall the covers on the cabinet.
After routing cables, use firestop putty to fill in the gap between the cables and the cabinet.
Copyright © Huawei Technologies Co., Ltd.
Figure 3-38
shows the signal cables routed
Figure 3-38
are for reference only.
3 Installation
75

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ups5000-e-480 kvaUps5000-e-360 kvaUps5000-e-440 kva

Table of Contents