Chore-Time Turbo-Cool Installation & Operator's Instruction Manual page 28

With open top 6" recirculating evaporative cooling
Table of Contents

Advertisement

System Start-Up6" Recirculating Evaporative Cooling
28
After the system runs for a while and turns off, the water level will rise
1.5-3.0'' above the level it was initially set at.
5.Open the valve in the pump discharge pipe.
6.Flush dirt and debris out of the Distribution Pipe by running the Pump with the
Ball Valves opened. After flushing the pipe out, close the Ball Valve at the end
opposite the Sump.
7.With the Pump running, open the Ball Valve above the pump as wide as possible
without excess water splashing out of the system.
8.If bleed-off is to be used, Adjust the Bleed Off Valve to a flow rate of 0.25 gpm
per 100 sq ft. of Evaporative Cooling Pad.
The correct amount of bleed-off depends on the amount of minerals and
chemicals in the water.
The bleed off rate can be adjusted over time, but should be maintained high
enough to prevent mineral deposits from accumulating on the face of the
Evaporative Cooling Pad.
MV1669U

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Turbo-Cool and is the answer not in the manual?

Questions and answers

Table of Contents