Commissioning - WAGNER EvoMotion 40-15 Original Operating Manual

Piston pump. flow rate 15 cm
Table of Contents

Advertisement

VERSION 12/2015
OPERATING MANUAL
6.6

COMMISSIONING

Observe all safety regulations in accordance with Chapter 4 and Chapter 7.2.
Emergency stop, see Chapter 7.3.
Preparation
Before every start-up, the following points should be observed as laid down in the
operating manual:
- Secure gun with safety clip.
- Check the permissible pressures.
- Check all connections for leaks.
- Check hoses for damage in accordance with Chapter 8.2.9.
Fill the pump with fl ushing agent
The devices are tested during manufacturing with emulsifying oil, pure oil or solvent.
Possible residues must be fl ushed out of the circuits with a solvent (fl ushing agent) before
commissioning.
- Fill the separating agent in accordance with Chapter 8.2.4.
- Fill the empty device with fl ushing agent in accordance with Chapter 8.2.7.
Pressure tightness test
- Gradually increase the pressure in pump with the pressure regulator until maximum
pressure is reached. Maintain the pressure for 3 minutes and check all connection
points for leaks.
- Depressurization in accordance with Chapter 7.5.
Filling with working material
- In accordance with Chapter 7.6.1.
ORDER NUMBER DOC2333558
31

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents