Installer Manual Siata V132-SFE-EV-VIRIDION - Programming
Third regeneration cycle duration
Note
The duration of the regeneration cycle can be set from 0 (OFF) to 99 minutes.
Set the third regeneration cycle duration.
A
Use
and
to set the duration.
B
Press
to validate and switch to the next parameter.
Fourth regeneration cycle duration
Note
The duration of the regeneration cycle can be set from 0 (OFF) to 99 minutes.
Set the fourth regeneration cycle duration.
A
Use
and
to set the duration.
B
Press
to validate and switch to the next parameter.
Chlorine cell control
Note
This option activate the chlorine producer control cell.
Note
For the boards without chlorine cell management hardware, even if the chlorine control is
activated, there will not be power in the back terminal ports 7-8. So it is not possible to
produce Cl.
Set the chlorine cell control.
A
Use
and
to set the control cell.
B
Press
to validate and switch to the next parameter.