Postrequisites
Do not place any additional load on the analyzer.
2.3

Connecting the system

2.3.1

Opening the enclosure

Use these procedures to make the electrical, power, and gas line connections.
1.
2.
Quick Start Guide
Mounting brackets are 4 mm (1/16 in.) thick stainless steel. Position the bolts in
such a way to allow maximum use of all thread length. Make sure that the fasteners
used are suitable for the load and surface the analyzer is mounted on.
Emerson recommends installing the analyzer in an upright (vertical) position; other
orientations may affect the measuring results.
If you want to increase security on the installation of the analyzer by thread-locking
the fittings, only do this with compounds compatible with the hazardous area zone
classification of the installation location.
Make sure the bolts are secure. Apply maximum torque permissible for the material
combination of the supporting structure.
Remove the lifting eyes and retain them for future use. Protect the threads with
plastic grommets and a suitable grease.
Make sure that the hinges are securely connected to the enclosure.
WARNING!
HEAVY FRONT HOUSING
The Rosemount
CT5800 front housing is heavy (30 kg (66.14 lb)). After removing the
captive bolts, provide support when opening the lid.
Failure to properly support the lid may cause injury to personnel.
CAUTION!
EQUIPMENT HAZARD
Inspect the hinges for damage before removing the M16 x 45 captive bolts to open the
housing.
Make sure no obstructions are in the opening radius when the front housing is opened.
Unscrew the 20 off M16 x 1.5 inch captive bolts holding the front and rear housings
of the enclosure together.