4.
5.
Step 3 (Optional) Deploying IVS in Stack Mode. For details, see
Mode.
Step 4 (Optional) Deploying MPUs in Cluster Mode. For details, see
Cluster
----End

5.10.2 Commissioning IPC6325 Cameras

Prerequisites
If multiple cameras are accessed, retain the connection of one camera and disconnect
connections from other cameras. After commissioning the connected camera, commission
other cameras in the same way.
Procedure
Step 1 Log in to the camera WebUI.
1.
2.
Step 2 For details about how to commission IP cameras and set parameters for them, see the
document delivered or click
1.
2.
3.
Issue 02 (2019-02-28)
In the search results, click Edit in the row where Parameter Name is NTPIPC and set
Value to 1.
Click Save. After the camera NTP synchronization function is enabled, the camera, after
being connected to the server, will automatically time-synchronize with the server.
Mode.
Configure the PC IP address and the camera IP address in the same network segment.
Enter the camera IP address (192.168.0.120 by default) in the address bar of the Internet
Explorer and press Enter button.
The following lists the requirements of the operating system and browser for logging in to the camera
through the WebUI.
Windows 7: Internet Explorer 8/9/10/11. Chrome 32+, and FireFox 35–51
Windows 8: Internet Explorer 10/11, Chrome 32+, and FireFox 35–51
Windows 10: Internet Explorer 11, Chrome 32+, and FireFox 35–51
Google Chrome 45 or later versions need to install the Internet Explorer tab plug-in.
Only 32-bit web browsers are supported.
Enter the preset user name admin and the preset password HuaWei123, and click Log
In.
Preview the site situation in real time and check the camera coverage through videos.
Adjust the lens if necessary.
Choose Settings > Network Configuration > Network Parameters, and set IP
address, Subnet mask, and Gateway IP address for the camera according to the site
plan.
Set camera stream type, primary stream, and secondary stream 1 parameters.
Copyright © Huawei Technologies Co., Ltd.
here
to download the document.
5 Power-On Commissioning
(Optional) Deploying IVS in Stack
(Optional) Deploying MPUs in
157

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents