System Commissioning; Checking Before Power-On; Powering On The System - Huawei SmartACU2000B Series User Manual

Smart array controller with pid modules, 800 v ac
Hide thumbs Also See for SmartACU2000B Series:
Table of Contents

Advertisement

SmartACU2000B smart array controller
User Manual (with PID modules, 800 V AC)

6.1 Checking Before Power-On

Before powering on the smart array controller, check that:
1.
2.
3.
4.
5.
6.
7.
8.

6.2 Powering On the System

Prerequisites
Issue 05 (2019-01-20)
6
The cabinet and all components are installed properly.
All upstream switches for the cabinet and all switches inside the cabinet are OFF.
All cables are connected correctly and securely, without exposed metal. Cables are
bound neatly, and cable ties are secured evenly and properly in the same direction. Extra
parts of cable ties are neatly cut. There is no unnecessary adhesive tape or cable tie on
cables.
Routing for power cables and signal cables meets the requirements for routing
strong-current and weak-current cables and complies with the cable routing plan.
The locking caps on all waterproof connectors in use at the bottom of the cabinet are
tightened, or the cable routing pipes (if used) are secured to the cabinet. All waterproof
connectors or cable routing pipes in use are applied with firestop putty. Idle waterproof
connectors at the bottom of the cabinet are plugged and the locking caps are tightened.
The cover on the USB port is tightened, and the USB cable inside the cabinet is secure.
The cabinet interior is clean, without dust, dirt, or foreign matter.
The paint on the cabinet exterior is intact. If paint flakes off, repaint that area to prevent
corrosion.
You have completed the power-on check.
You have put on insulation gloves.
The smart array controller cabinet is reliably grounded.
The power voltage of the smart array controller is within the operating voltage range,
and the three-phase input voltage is within the PLC/PID module operating voltage.
All upstream switches for the smart array controller and all switches inside the cabinet
are OFF.
Copyright © Huawei Technologies Co., Ltd.

System Commissioning

6 System Commissioning
82