Start-Up Tasks

Complete all the Installation tasks (see details on page 14) before starting these Start-Up tasks.
Complete the Start-Up tasks in the following order:
Task Description
1
Insert the rectifiers
2
Complete the Pre-Power-Up Checklist
3
Connect to the ac supply
4
Configure the dc power system (some models only)
5
Apply dc power to dc-powered equipment

Task 1 - Inserting the Rectifiers

Step 1 - Unpack the rectifiers
Unpack the rectifiers and inspect them carefully for possible transport damage.
Report any damage immediately using a completed Equipment Incident Report on
page 77.
Step 2 - Fit first rectifier
1
2
3
4
28
Do NOT install the rectifiers until the room has been cleaned and is dust free.
Do NOT switch on the ac supply at this stage.
Keep the original packaging to return a rectifier for replacement or repair, if required.
Align the rectifier with the left side of the shelf.
Push in the rectifier until the retaining screw contacts the shelf.
Check the rectifier's rear connector is correctly aligned with the shelf connector,
or damage may occur.
Tighten the retaining screw to 1.5Nm (13.3 inch-pounds). This will locate the
rectifier in its rear connector.
Copyright © 2007-2010 Eaton Corporation. All Rights Reserved.
IPN 997-00012-62E
Reference
See details on page
See details on page
See details on page
See details on page
See details on page
June 2010
28
29
29
30
31

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents