Step 4 - Check terminations, secure cables and test insulation
1
2
3
Procedure complete
Task 9 - Connect to the AC Supply Point
Step 1 - RM3-400/410/420 systems with IEC cord sets
If the RM3-400/410/420 has permanently connected ac cords then go to Step 2.
Connect one of the cord sets provided to each IEC connector on the rear of the RM3-
400/410/420.
Step 2 - Connect at the ac supply point
1
2
3
4
Procedure complete
Do not switch on the ac supply at this stage.
Installation Completed
Installation of the RM3-400/410/420 is now complete. Follow the instructions in Start-Up on
page
28
to make the system operational.
Check all terminations are correct and are tightened.
Secure the cables with cable ties to ensure there will be no strain on the terminals.
Test the insulation resistance of the cables.
If the cord sets are missing or must be replaced then refer to Spare Parts on page
replacement items.
Check the ac supply point is isolated.
Connect the ac cords to the ac supply point.
Label the connection at the ac supply point.
Secure the cords to ensure there is no strain on the terminals.