Step 3 - Repeat for other rectifiers or fit blank panels
If not already fitted, fit rectifier blank panels in any vacant rectifier positions.
Procedure complete
Task 2 - Pre-Power-Up Checklist
Complete the checklist to confirm initial work is complete before progressing further.
All cabling is installed, securely tied and correctly insulated
Ground bonding is correct (see details on page 17)
Output cabling has the correct polarity
A registered electrician or other suitable approved person has checked the integrity of the
installed cabling
All covers are in place and all empty rectifier slots are covered with blanking panels
Equipment to be powered is switched off
RM3-400/410/420 is disconnected from the ac supply
The site is clean.
Task 3 - Connect to the AC Supply
Connect the RM3-400/410/420 to the ac supply.
1
All rectifiers start up (after the startup delay).
•
The rectifier alarm LEDs will turn on for a short time. The rectifier yellow alarm LEDs
•
will flash.
If an SC200 or SC100 system controller is fitted (some models only):
2
The system controller will turn on (green Power On LED is on) when the rectifiers start.
•
When the system controller has completed its start-up sequence (rectifiers are
•
registered) the rectifier yellow alarm LEDs will turn off.
•
A registered electrician (or suitably qualified person) must check the integrity of
the installed cabling, BEFORE the dc power system is powered up.