Step 1
Identify the Tube Assembly Sections required for the specific auger model being assembled.
See the tube section identification page previous to this page.
Step 2
Place tubes on assembly stands. Place stands 12" or less from the end of the tube. Placing stands
farther than 12" from end of the tube may cause damage to the tubes (see Figure 2.1).
12" (MAX.)
Or Less On
Both Ends
Step 3
(Only for T832/T836/T842) Locate bolt bag PN 1300060249-00. Slide the flighting from the Intake
and Discharge Tubes. Align flighting as shown in Figure 3.1 to make continuous. Connect the flighting
using (2) 1/2" x 2-1/2" Hex Bolts and (2) 1/2" Stover Lock Nuts (see Figure 3.1). Slide the Intake and
Discharge Tubes and put together, connect them with (8) 3/8" x 1" Flange Lock Bolts and (8) 3/8"
Flange Lock Nuts (see Figure 3.1).
Intake Tube
ASSEMBLY
TUBE ASSEMBLY
Discharge Tube
Figure 3.1: Tube Connection
*Drive Shaft not shown for Clarity
B3
1300060439-35-00

Advertisement