Figure 6-1
outlines how to prime, equilibrate, and purge a sparge-based Separations
Module that is new or dry.
Note:
All flow chart references refer to sections in the Waters 2690 Separations Module
Operator's Guide.
Figure 6-1 Preparing a New or Dry Separations Module for Operation (Sparge-Based Unit)
50
Recommended Preparation Procedures
Start
Fill the Solvent
Reservoirs with
Fresh Solvent
Filtered and
Degassed by
Vacuum Filtration
(See Section 2.6.3)
Sparge all
Reservoirs at an
Initial Sparge Rate
100%
of
for at
Least 15 min. Set
an Idle Sparge Rate
30
50%
of
to
(See Section 4.4.4)
Perform a Dry
Prime (to Fill Each
Solvent Line) See
Section 4.4.1
Perform a Wet
Prime (for One of
5
the Solvents) for
5.00
min at
mL/min
(See Section 4.4.2)
Repeat the Wet
Prime (at the Same
Rate and Time) for
Each Solvent
To Make a Gradient
Run (for Example,
A:B), Set the A and
B Composition
Fields in the Status
50%
Screen to
,
2
then Wet Prime for
5.00
min at
mL/min
(See Section 4.4.2)
Equilibrate for a
Minimum of 10
Column Volumes
(See Section 4.4.5)
Purge the Injector
for a Minimum of 6
Loop Volumes
(See "Purging the
Injector" in
Section 4.4.2)