SECTION 8 - GENERAL SPECIFICATIONS & OPERATOR MAINTENANCE
10. Verification Of The Overload Detection
Setting (Toucan 800 only)
Interval - Check after every 6 months of operation.
a.
Place a 200 kg load evenly distributed on the
platform floor.
b.
Position the Platform/Off/Ground selector switch
to "Platform Con trols". ensure the lower
emergency stop is not activated.
c.
Apply a slight pressure F1 on the platform and
ensure that :
An acoustic alarm sounds.
The corresponding LED lights up.
Every function is disabled from the platform con-
trols.
d.
Position the Platform/Off/Ground selector switch
to "Ground Controls" and ensure that :
An acoustic alarm sounds.
The corresponding LED lights up.
Every function disabled from the ground con-
trols.
e.
Apply a slight traction F2 on the platform and
ensure that the acoustic alarm stops.
8-12
Machine manufactured before 2010
Machine manufactured after 2010
– JLG Lift –
31210031