3. The tightening of the nuts should be done in stages. Following the recommended
sequence, tighten nuts per wheel torque chart.
1st Stage
45 ft. lbs.
(60 Nm)
4. Wheel nuts should be torqued before first road use and after each wheel removal.
Check and torque every 3 months or 150 hours of operation.
7.8
SUPPLEMENTAL INFORMATION ONLY APPLICABLE TO
CE/UKCA MACHINES
The following information is provided in accordance with the requirements of the
European Machinery Directive 2006/42/EC or Supply of Machinery (Safety) Regulations
2008 No. 1597.
The A-Weighted emission sound pressure level at the work platform is less than 70 dB
(A).
The guaranteed Sound Power Level (LWA) per European Directive 2000/14/EC (Noise
Emission in the Environment by Equipment for Use Outdoors) or Noise Emission in the
Environment by Equipment for use Outdoors Regulations 2001 No. 1701 based on test
methods in accordance with Annex III, Part B, Method 1 and 0 of the directive, is 104 dB
(A) for machines equipped with Stage IIIA engines and 108 dB (A) for machines
equipped with Stage V engines.
The vibration total value to which the hand-arm system is subjected does not exceed
2,5 m/s
. The highest root mean square value of weighted acceleration to which the
2
whole body is subjected does not exceed 0,5 m/s
154
Table 14. Wheel Torque Chart
TORQUE SEQUENCE
2nd Stage
100 ft. lbs.
(140 Nm)
31222384
2
.
3rd Stage
180 ft. lbs.
(252 Nm)