Preparation For Commissioning; Basic Flushing - WAGNER Cobra 40-10 Translation Of The Original Operating Manual

High-pressure double diaphragm pumps
Table of Contents

Advertisement

VERSION 07/2014
OPERATING MANUAL
6.8.2

PREPARATION FOR COMMISSIONING

Impurities in the spraying system!
Clogging of the spray gun
Flush the spray gun and paint supply with a suitable fl ushing agent before
commissioning.
6.8.3

BASIC FLUSHING

1 Place empty tank (5) under return tube (4).
2 Place suction hose (7) in a tank with cleaning
agent (6).
3 Adjust the pressure regulator (1) to approx.
0.05 MPa; 0.5 bar; 7.25 psi.
4 Open relief valve (3).
5 Slowly open the ball valve (2).
6 Adjust the air pressure on the pressure regulator (1)
so that the pump runs smoothly.
7 Rinse the system until the cleaning agent that
fl ows into the tank (5) is clean.
8 Close ball valve (2).
9 Reverse the relief valve (3).
10 Point the gun, without nozzle, into tank (5) and
open it.
11 Slowly open the ball valve (2).
12 Flush until clean fl ushing agent fl ows from the gun.
13 Close ball valve (2).
14 When there is no pressure remaining in the system, close the gun.
15 Secure the gun.
16 Dispose of the contents of the tank (5) according to the local regulations.
Note:
During the fl ushing procedure, briefl y press both valve depressors (V).
ORDER NUMBER DOC2340851
NOTICE
B_04240
1
2
3
9
4
5
7
6
V
32

Advertisement

Table of Contents
loading

This manual is also suitable for:

Cobra 40-25

Table of Contents