6.7 SYSTEM TEST

The Control System Incorporates a built-in system test to
check the system components and functions. To use this
function, use the following procedures.

Platform Test

1. Position the Platform/Ground select switch to the
Platform position.
2. Plug the analyzer into the connector at the base of
the platform control box.
3. Pull out the Emergency Stop switch.
3121198
SECTION 6 - JLG CONTROL SYSTEM
4. The analyzer screen should read:
5. Use the arrow button to reach SYSTEM TEST. Hit
Enter. The analyzer will prompt you asking if you
want to activate the system test; hit Enter again to
activate.
6. Follow the flow path in Figure 6-5., System Test Flow
Chart - Platform Tests and go through the compo-
nent tests. Hit the ESC key during any part of the
test to return to the main menu without completing
all tests or wait until all tests are complete. During
the TEST ALL INPUTS sequence, the analyzer
allows control switches to be operated and shows if
they are closed (CL) or open (OP).