energized (controlled) through connectors TB20 and TB21 (TB21 available only
in the 40 kW UPS frame). The default voltage of the shunt trip coil is 24 Vdc.
Figure 14. Battery trip wiring, TB20
Figure 15. Battery trip wiring, TB21
A
External battery breaker
1
Pin 1, shunt trip coil +
2
Pin 2, shunt trip coil -
5.3
power cabling
For the 93PS product line, there are two different battery cabinets: EBC-S and
EBC-L. The 93PS 8-40 kW UPSs use 32 battery blocks per string.
If you connect the C-model 93PS UPS to an external battery cabinet, note
that you have to install supplementary fuses or a supplementary breaker in
addition to the internal battery breaker to ensure safe operation.
Note: Do not connect battery strings with different battery quantity and voltage
in parallel.
Power and control wiring for the EBC-S and EBC-L cabinets are supplied with
the cabinets. The battery cabinet can be located freely of the 93PS UPS
cabinet. All the wiring goes through the back wall of the UPS cabinet.
©
Eaton Corporation plc 2016. All rights reserved.
Installing UPS external battery cabinet and battery
3
Pin 3, AUX contact
4
Pin 4, AUX contact return