Commissioning after a long storage time

If the inverter was not operational for a longer period of time, it is possible that you must form
the DC-link capacitors before switching on.
Form the DC-link capacitors in the following cases:
● If the inverter was not operational for longer than one year.
● If the date of manufacture of the inverter was more than one year ago when commissioning
the drive system for the first time. The date of manufacture is coded in the serial number
(see the next paragraph).
You form the DC-link capacitors by connecting power to the inverters as shown below.
U [V]
100
75
50
25
Figure 6-1
Data of manufacture of the inverter
The date of manufacture of the inverter is coded in positions 3 - 6 of the serial number.
Figure 6-2
Power Module PM240-2
Hardware Installation Manual, 08/2017, A5E33294624B AG
0
0,5
1
2
Forming the DC-link capacitors
Data of manufacture in the serial number (example, April 21, 2013)
6.2 Commissioning after a long storage time
3
4
5
Service and maintenance
t [h]
6
7
8
69

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents