Installing/mounting
4.4 Mounting the Power Modules
4.4.1

Sequence for installing the Power Module

During installation, comply with the sequence listed below.
Frame sizes FSA ... FSC
1. Prepare the cabinet.
2. Mount the shield plates.
3. Install the Power Module.
4. If you are using a Brake Relay or Safe Brake Relay:
Install the Brake Relay next to the inverter.
Frame sizes FSD ... FSF
1. Prepare the cabinet.
2. If you are using a Brake Relay or Safe Brake Relay:
Install the Brake Relay on the rear side of the shield plate.
3. Mount the shield plates.
4. Install the Power Module.