3.
MEASURE TORQUE CONVERTER SLEEVE RUNOUT
(a)
Temporarily mount the torque converter to the drive
plate. Set up a dial indicator.
If runout exceeds 0.30 mm (0.0118 in.), try to correct by
reorienting the installation of the converter. If excessive
runout cannot be corrected, replace the torque converter.
HINT:
Mark the position of the converter to ensure cor-
rect installation.
(b)
Remove the torque converter.
TRANSMISSION INSTALLATION
1.
INSTALL TORQUE CONVERTER IN TRANSMISSION
If the torque converter clutch has been drained and
washed, refill with new ATF.
Fluid type:
AFT DEXR0N®n
2.
CHECK TORQUE CONVERTER INSTALLATION
Using calipers and a straight edge, measure from the in-
stalled surface to the front surface of the transmission.
Correct distance:
(1FZ-FE)
More than 37.2 mm (1.465 in.)
(1HD-T)
More than 43.8 mm (1.724 in.)
3.
PLACE TRANSMISSION AT INSTALLATION POSITION
Jack up and push the transmission fully into position.
4.
INSTALL TRANSMISSION BOLTS
(a)
Install the transmission with the bolts.
Torque:
72 N-m (730 kgfcm, 53 ftlbf)
(b)
Connect the wire harness to the transmission and trans-
fer with the clamp.
(c)
Connect the connectors to the transfer.