Group 5

5.3 Installation

For adaption to the production line several works have to be carried out and
operating parameters have to be set before start of operation.

5.3.1 Mains supply

The device does not have a mains switch and should be only
connected to an easy accessible socket close to the installation
location!
The LEIBINGER JET3up should be connected to AC voltage 100 - 240 V AC, 50 – 60
Hz with an appropriate plug. The socket should be provided with a clear designation
(e.g.: JET3up).
After connecting to the mains power supply the initialization of the device will be
carried out automatically. After this process the JET3up is ready for operation.
You will find further information regarding the initialization in the
chapter 6.5.2 First initialization of the device

5.3.2 Grounding - Potential equalization

Grounding (Potential equalization)!
 In case of a non existing grounding or that the grounding of the
 These dangers or demolitions can happen for example because of
Especially for countries without existing protected earth connection, there is a special
grounding point located at the side of the printer.
This threaded socket must be connected to ground if there is no ground pin in the
mains socket/plug.The threaded case is sealed inwards and thus IP 65 conform. With a
screw and a ring terminal (cable lug) the grounding can be fixed easily.
JET3up
Transport/Start up
WARNING – MAINS SUPPLY
INFORMATION
WARNING
printer is not carried out properly, this could cause serious injury
or death and it can also cause malfunctions or damages at the
printer!
electrostatic discharge (ESD) or potential difference!