5 Commissioning

5.1 Control panel

Refer to the connection instructions supplied with the control
panel..

5.2 Check points before commissioning

Hydraulic circuit
- Check that the installation and boiler are adequately filled with
water and correctly irrigated and bled (Pmin: 0.8 mbar).
- Check that there are no leaks on the hydraulic connections.
Gas circuit
- Check that the appliance is properly set for the type of gas used.
- Check the supply pressure.
- Check the tightness of the gas circuit.

5.3 Commissioning procedure

- Ensure that the boiler is switched off
- Remove the front casing
- Open the main gas supply
- Open the boiler control panel (see chapter "Control panel
assembly")
- Check the electrical connection
- Fill the installation with water and check hydraulic tightness (Pmin:
0.8 bar)
- Vent the heating installation
- Fill the condensates siphon with water
- Check the connection of the combusted gas evacuation and the air
inlet
- Empty the gas inlet
- Open the gas valve on the gas pipe to the boiler
- Check the gas connection
- Turn the boiler on
- Turn the main switch to
- The boiler type is displayed on the screen for 5 seconds
- Provoke a heating request
- The boiler starts to operate
- Check the settings (See "Gas settings"). If necessary, correct the
settings
03/10/2012 - 300015171-001-01
Electrical connectors
- Check that the connectors under the control panel are correctly
fitted.
- Check the presence of PSU in the control panel.
- Check the earth.