4.4 Hydraulic connections
4.4.1
Regulations
Installation must be carried out in accordance with the prevailing
regulations, the codes of practice and the recommendations in these
instructions.
Installing the boiler in new installations
(installations less than 6 months old)
- Clean the installation with a universal cleaner to eliminate debris
from the appliance (copper, hemp, flux).
4.4.2
Hydraulic connection of the heating circuit
Flow connection
Return connection
03/10/2012 - 300015171-001-01
- Thoroughly flush the installation until the water runs clear and
shows no impurities.
Installing the boiler in existing installations
- Remove sludge from the installation.
- Flush the installation.
- Clean the installation with a universal cleaner to eliminate debris
from the appliance (copper, hemp, flux).
- Thoroughly flush the installation until the water runs clear and
shows no impurities.
C 230 ECO
25