3.3
Start Up Procedure Checklist
Item
1
2
3
4
5
6
7
NOTE:
IMPORTANT!
When switching Off the system you MUST wait 30 seconds before switching the main
disconnect back On. You may experience communication issues if you do not wait the
required 30 seconds.
14
v 1.4 — September 2015
Connect power/thermocouple cables between the mold and controller (if
required).
Connect option cables (if required).
Connect the controller to the power source.
Switch the controller ON.
Load a mold setup.
Touch START to run the system.
Check that the controller is functioning correctly.
There are no Controller to Mold Interconnection details included in this User Guide.
Please see the Mechanical / Electrical Engineering Documents provided with the
controller.
Step
Start Up Procedure Checklist
Altanium Neo2