Argon 18 E-119 TRI+ Assembly Manual page 46

Hide thumbs Also See for E-119 TRI+:
Table of Contents

Advertisement

E-119 TRI+: 16. Top Tube Box Installation
(D)
(D)
1. Attach Top Tube Box (TTB) to frame
using fastening screws (D). Do not tighten.
4. If cables are already installed, make a small
incision (indicated above) to insert cables
into the TTB and avoid rerouting bike's cables.
2. Ensure Di2 cables are routed the same way
as brake cables. (See Assembly Guide, p.29)
*
(C)
*
(C)
*
(C)
5. Once cables are routed, install stem cap (B)
using the screws (C). Tighten screws to 1Nm.
3. Ensure mechanical drivetrain cables
are routed through the TTB's top
and into the frame.
(D)
(1Nm)
*
6. Line up TTB with stem cap to desired fit
and tighten fastening screws (D) to 3Nm.
(3Nm)
(D)
45

Advertisement

Table of Contents
loading

This manual is also suitable for:

E-119 tri

Table of Contents