Options Cabinet Installation

2.4
2.4.1

Unloading the Options Cabinet from the Pallet

To remove the Options cabinet from the pallet, refer to paragraph 2.2.2.
2.4.2

Joining the Options Cabinet to the UPS Cabinet

To join the Options cabinets to the UPS, perform the following steps. Refer to
Figure 2---7 for non-permanent installation or Figure 2---8 for permanent installation
of the Powerware 9330 (IBM 9910 20 kVA) UPS.
NOTE: The cables used in step 8 are coiled outside the Options cabinet and are
attached at the factory to the input and output terminals of the Options
cabinet.
1.
Roll the Options cabinet to a spot near the left side of the UPS.
2.
Remove left front solid panel, and right front vented panel from the Powerware
9330 (IBM 9910 20 kVA) UPS cabinet. Front panels are secured with magnetic
latches and are removed by pulling panels straight forward to disengage
magnetic latches (see Figure 2---1).
3.
Remove screws securing UPS cabinet internal safety shield panel and remove
panel to gain access to wireway.
4.
Remove front vented panel from Options cabinet. The front panel is secured
with magnetic latches and are removed by pulling panels straight forward to
disengage magnetic latches.
5.
Remove left side outside panel from UPS cabinet. Retain hardware.
6.
Remove left side panel from Options cabinet. Retain hardware.
7.
Install side panel removed from the Options cabinet to the left side of the UPS
cabinet. Secure with screws removed from UPS cabinet.
8.
Route the input and output cables from the Options cabinet through cutout in
UPS cabinet side to the UPS wireway.
9.
Push the Options cabinet against the left side of the UPS cabinet.
10.
If permanently mounting the system, proceed to step 16; otherwise, proceed to
step 11.
11.
Secure the Options cabinet in position by lowering the leveling feet, until
cabinet is not resting on the casters and the cabinet is level.
12.
Secure the front of Options cabinet to the front of the UPS cabinet by sliding
the angle grounding/mounting bracket, from installation kit, behind the base of
the Options and UPS cabinets with the bottom angle facing outward (see
Figure 2---7). Use hardware provided in the kit to secure the bracket.
Powerware 9330 (IBM 9910 20 kVA) Installation and Operation