Installation

UPS and Battery Cabinet Installation

Use the following procedure to install the UPS and battery cabinets:
30
1. Place the UPS near the equipment to be protected. The UPS
should be well ventilated and away from direct sunlight or
other heat source.
Figure 3 shows the different UPS stacking configurations.
NOTE Do not place more than three battery cabinets in one stack. The UPS cabinet
must be placed on top of the battery cabinets.
UPS
Cabinet
Battery
Cabinet
NOTE You can install additional battery cabinets while the UPS is operating, but
confirm the UPS is not in Battery mode (see page 43).
2. Verify the circuit breaker on all battery cabinets is in the
OFF (O) position (see Figure 4).
3. Remove the battery connector guard. Plug the battery cord into
the external battery connector on the UPS. All battery
connectors are polarized to prevent incorrect connection.
Powerware
Air Vents
Figure 3. Cabinet Setup
9 Prestige Series User's Guide (3000 VA)
®
Battery Cabinet
UPS Cabinet
:
www.powerware.com