Figure 3-22 Connect the cramped connectors

Verifying the Installation

Make sure that you have turned off the power before checking the installation to avoid bodily injury and
device damage.
After installing the switch, verify the installation against the following list. For the successful installation,
all items must be normal.
Table 3-4 Installation checklist
The PGND cable is correctly grounded.
Fan trays are correctly installed and have a tight
contact with the backplane.
PSUs are correctly installed and have a good
contact with the frames.
PSUs are powered on with the power switches at
the ON position.
Power cords are correctly connected.
MPUs are correctly installed and have a good
contact with the backplane.
Interface cards are correctly installed and have a
good contact with the backplane.
Item
3-21
Result
Yes
No
Remarks