Completing The Cp Pii Upgrade - Nortel Meridian Meridian 1 Upgrade Manual

81c igs to cs 1000m mg cp pii fnf upgrade
Hide thumbs Also See for Meridian Meridian 1:
Table of Contents

Advertisement

Completing the CP PII upgrade

Communication Server 1000M and Meridian 1
Procedure 49
Testing Core/Net 1
From Core/Net 1, perform these tests:
1
Perform a redundancy sanity test:
LD 135
STAT CPU
TEST CPU
2
Check the LCD states:
a.
Perform a visual check of the LCDs.
b.
Test LCDs:
LD 135
TEST LCDs
DSPL ALL
3
Test the System Utility cards and the cCNI cards:
LD 135
STAT SUTL
TEST SUTL
STAT CNI c s
TEST CNI c s
4
Test system redundancy:
LD 137
TEST RDUN
Performing the upgrade
Load program
Get status of CPU and memory
Test CPU
Load program
Test LCDs
Load program
Get status of the System Utility (main and
Transition) cards
Test System Utility (main and Transition)
cards
Get status of cCNI cards (core, slot)
Test cCNI (core, slot)
Load program
Test redundancy
81C IGS to CS 1000M MG CP PII FNF Upgrade
Page 167 of 284

Advertisement

Table of Contents
loading

This manual is also suitable for:

Meridian 1Communication server 1000m

Table of Contents