Commissioning

7.1

Commissioning 3RW55 and 3RW55 Failsafe soft starters

Procedure
1. Mount the 3RW55 or 3RW55 Failsafe (Page 55) soft starter.
2. Connect the 3RW55 or 3RW55 Failsafe soft starter (Page 74).
3. Set the required language, the current date and time and the rated operational current.
First commissioning of the High Feature 3RW5 HMI (Page 127)
4. Parameterize the 3RW55 or 3RW55 Failsafe soft starter for your application (Page 89).
For support, use the application wizard (Page 92) and automatic parameterization
(Page 132).
5. Conduct a test of the application in test mode (Page 221).
6. Optionally, you can run diagnostics (Page 257) including Self-test (user-test) (Page 264) to
test correct functioning of the 3RW55 or 3RW55 Failsafe soft starter.
7. Set the access protection (optional).
– Local access protection (PIN) (Page 237)
– User login and logout (Page 242)
– Sealing 3RW55 and 3RW55 Failsafe soft starters (optional) (Page 126)
Note
Last changed parameters
For each parameter set, you can view and directly modify the last 10 changed parameters.
Menu: "Parameters > Soft Starter > Parameter set 1 / 2 / 3 > Last changed parameter"
Result
The 3RW55 or 3RW55 Failsafe soft starter is ready for operation and protected from external
access.
You will find additional information on operating modes and the respective control priority in
chapter Operating modes and master control function (Page 32).
SIRIUS 3RW55 and 3RW55 Failsafe Soft Starters
Equipment Manual, 02/2022, A5E35630887002A/RS-AF/006
7
125