PREPARATION

3.2.1

Introduction

Your Model 1000 Analyzer was started and checked out before it left the factory. Program
parameters were installed in the system and documented in the "PC Config Report" furnished with
your GC System.
3.2.2

Site Selection

Follow these guidelines for site selection:
(1)
Provide adequate access space for performing maintenance and adjustments.
(a)
Allow a minimum of 3 feet (.9 m) in front for operator access.
(b)
Allow a minimum of 15 inches (38 cm) at the rear and left side for case removal.
(c)
If possible, mount the Analyzer components in a vertical stack configuration; it
provides the greatest operator convenience.
(2)
Install the Analyzer as close as possible to the sample stream.
(3)
Install the GC Controller no further than 2000 feet (610 meters) away from the Analyzer.
(4)
Ensure that exposure to radio frequency (RF) interference is minimal.
3-14
Observe Precautions and Warnings
1
Plan Site Location
2
Obtain Supplies and Tools
3
Install Analyzer Wiring
4
MODEL 1000