Sample Systems Requirements - Emerson Daniel Danalyzer 1000 Hardware Reference Manual

Gas chromatograph
Table of Contents

Advertisement

MODEL 1000
3.1.6

Sample Systems Requirements

Observe the following guidelines for installing GC sample systems:
Sample Line Length: If possible, avoid long sample lines. In case of a long sample line, flow
velocity can be increased by decreasing downstream pressure and using by-pass flow via a
speed loop.
Sample Line Tubing Material:
-
Use stainless steel tubing for noncorrosive streams.
-
Ensure tubing is clean and free of grease.
Dryers and Filters in Sample Line:
-
Use small sizes to minimize time lag and prevent back diffusion.
-
Install a minimum of one filter to remove solid particles. Most applications require
fine-element filters upstream of the Analyzer.
-
Do use ceramic or porous metallic type filters. Do not use cork or felt filters.
Pressure Regulators and Flow Controllers in Sample Line: Do not use types containing cork or
felt filters, or absorbent diaphragms.
Pipe Threads, Dressing: Do use Teflon tape. Do not use pipe thread compounds (dope).
Valving:
-
Install a block valve downstream of sample takeoff point for maintenance and
shutdown.
-
Block valve should be gate valve or cock valve type, of proper material and packing,
and rated for process line pressure.
INSTALLATION AND SETUP
Observe Precautions and Warnings
1
Plan Site Location
2
Obtain Supplies and Tools
3
Install Analyzer Wiring
4
SEP 2005
3-13

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rosemount analytical 1000

Table of Contents