SYSTEM START-UP

To perform system start-up, follow these steps:
(1)
For system start-up, run an analysis of the calibration gas.
(a)
Ensure that the Stream switch for the calibration gas has been set to AUTO (see last
step, previous section).
(2)
Run the GC System in "Single Stream" mode.
(a)
To operate the GC System with a PC and the software MON2000, refer to the
MON2000 Software for Gas Chromatographs User Manual (P/N 3-9000-522).
or
(b)
To operate the GC System from the front panel keyboard and LCD, refer to Section
4, "Operation," this manual.
For process GC systems that handle multiple streams and are equipped with optional purge
system components, you must also set up solenoid purge flow prior to normal operation of the
GC system. For more information about this, along with a procedure for setting solenoid
purge flows, see Appendix E, this manual.
3-96
Perform Leak Checks
7
Purge Carrier Gas Lines
8
Purge Calibration Lines
9
Start Up GC System
10
MODEL 1000
INSTALLATION AND SETUP