Site Preparation Checklist for an ACX5000 Router

The checklist in
Table 23 on page 78
an ACX5000 router installation.
Table 23: Site Preparation Checklist
Item or Task
Environment
Verify that environmental factors such as
temperature and humidity do not exceed
router tolerances.
Power
Measure the distance between external
power sources and router installation site.
Calculate the power consumption and
requirements.
Rack or Cabinet
Verify that your rack or cabinet meets the
minimum requirements for the installation
of the router.
Plan rack or cabinet location, including
required space clearances.
Secure the rack or cabinet to the floor and
building structure.
Cables
summarizes the tasks you need to perform when preparing a site for
For More Information
"ACX5000 Router Environmental
Specifications" on page 83
"AC Power Specifications for an
ACX5000 Router" on page 73
"Rack Requirements for an
ACX5000 Router" on page 86
"Cabinet Requirements for an
ACX5000 Router" on page 85
"Clearance Requirements for
Airflow and Hardware
Maintenance for an ACX5000
Router" on page 81
Performed By
Date
78