3.4
Initial commissioning using servo (booksize) as an
example
The commissioning example described in this section shows all the necessary con-
figuration and parameter settings and testing routines. The commissioning proce-
dure is performed using the STARTER commissioning tool.
Requirements for commissioning
1. The commissioning requirements have been met.
–> see Section 2.1
2. The checklist for commissioning has been completed and all items are O.K.
–> see Section 2.2
3. STARTER is installed and ready to run.
–> see the "read me" file on the STARTER installation CD.
4. The electronics power supply (24 V DC) is switched on.
E Siemens AG, 2004. All rights reserved
SINAMICS S120 Installation and Start-Up Manual, 12/04 Edition

Initial commissioning using servo (booksize) as an example

Commissioning
3-53