Connect AC

- Insert the AC cables through the AC conduit and connect them to the
- Torque wires with a torque of 1.7 ft. lbf.
- Close the connection area
- Switch DC disconnect to the "ON" position
- Switch AC disconnect to the "ON" position

Start up Operation

Configuring your Inverter

Factory pre-
Your FRONIUS IG unit has been pre-configured in the factory and is
set configura-
ready for operation.
tion
After mounting the FRONIUS IG unit to the wall and connecting it to the
solar modules (DC) and to the grid (AC), all you have to do is turn on the
AC and DC circuit disconnects.
- as soon as the photovoltaic modules produce sufficient power, the
- the orange LED indicates that the feed-in mode of the FRONIUS IG will
- after the FRONIUS IG unit has started feeding the energy into the grid,
- the LED light continues green as long as power is fed into the grid. This
AC terminals labeled "L1", "L2" and „N", as well as to the ground termi-
nal (1), labeled
.
NOTE! Use minimum AWG 10, min. 167 °F (75 °C), copper wire
for all grounding cables.
status LED lights up orange and the screen displays the startup proce-
dure
begin shortly
the LED light turns green
confirms that the FRONIUS IG is operating properly and feeding energy
into the grid.
54