OPERATION

Configuration Mode

When the UPS is in Configuration mode, the front panel indicators
represent the configuration options. Use the control buttons
(On button, Off
configuration. Figure 23 shows the indicators and Table 8 explains the
corresponding options.
1.
2.
3.
NOTE The UPS exits Configuration mode automatically after two minutes.
4.
24
EATON Powerware
button, and
Press and hold the On button and the
for one beep (approximately five seconds). The UPS transfers to
Configuration mode.
The indicators flash briefly and then display the enabled options.
Press the On button to scroll through the options. Each time you
press the button, the UPS beeps. The indicator for the selected
option indicates the current setting; flashing represents disabled
options (see Figure 23 and Table 8).
Scrolling past the last indicator returns to the first configuration
option.
If you press the On button and nothing happens, the UPS is still in
Operation mode. Repeat Step 1 for one beep ONLY to enter
Configuration mode, and then perform Step 2.
Press the Off
button button ONCE to select the Voltage option
or to toggle the Site Wiring Fault Alarm on or off.
Press the
button to confirm the selection and exit Configuration
mode. If you do not press the
original settings.
®
5125 (9910-E33) UPS Installation Guide for IBM
button) to modify the UPS
button simultaneously
button, the UPS defaults to the
®
S
Applications
164201695 Rev 1

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Powerware 5125 9910-e33

Table of Contents