8
Touch [3 CSRC Communications Test].
The CSRC Communications Test Screen will be displayed.
Touch [Start] to perform the communication test. On completing the
test, touch [Return] to restore the CSRC Setting Screen.
9
Touch [Close] to return to the IP NIC Setting Screen.
If further changes are required, touch the desired key.
10
After you have changed the settings, turn off the sub power, then turn
off and on the main power.
!
Detail
When you turn off and on the main power, you need to wait at least 10
seconds to turn on after turning off. If you do not allow a sufficient interval
in between, the machine may not run correctly.