CHAPTER 4
Site Preparation
Site Preparation Checklist for a J-EX8200 Switch
Table 30: Site Preparation Checklist
Item or Task
Environment
Verify that environmental factors such as
temperature and humidity do not exceed switch
tolerances.
Power
Measure distance between external power
sources and switch installation site.
Calculate the power consumption and
requirements.
Site Preparation Checklist for a J-EX8200 Switch on page 63
General Site Guidelines for J-EX Series Switches on page 64
Site Electrical Wiring Guidelines for J-EX Series Switches on page 65
Environmental Requirements and Specifications for J-EX Series Switches on page 66
The checklist in Table 30 on page 63 summarizes the tasks you need to perform to prepare
a site for installing a J-EX8200 switch.
For More Information
"Environmental Requirements and
Specifications for J-EX Series
Switches" on page 66
"AC Power Specifications for
J-EX8200 Switches" on page 81
"Power Requirements for J-EX8216
Switch Components" on page 82
"Calculating Power Requirements for
a J-EX8216 Switch" on page 85
"Calculating the J-EX8200 Switch
Fiber-Optic Cable Power Budget" on
page 91
"Calculating the J-EX8200 Switch
Fiber-Optic Cable Power Margin" on
page 92
Performed By
Date
63