This section describes how to operate the UPS.
NOTE
Before starting the UPS, ensure all installation tasks are complete and a preliminary startup has
been performed by authorized service personnel. The preliminary startup verifies all electrical
interconnections to ensure the installation was successful and the system operates properly.
Read these instructions and have a thorough understanding of UPS operation before attempting
to operate any of the controls. The UPS is configured to operate with one of following nominal
voltages: 380, 400, or 415 Vac. Before operating the UPS, confirm the UPS nominal voltage and
frequency from display by selecting Settings -> Info. If the UPS need to be operated with another
voltage or frequency, contact your closest Santak office or Santak authorized partner.
The UPS in not a measuring device. All displayed measurements are only approximate values.

6.1. Ups Controls and Indicators

6.1.1.

Control Panel

The control panel is used to set up and control the UPS, and to monitor UPS operation. For a
description of the UPS control panel functions, see Section
6.1.2.

LPS

The LED Power Show (LPS) consists of two rows of LEDs located on the left and right sides
of the UPS cabinet door. The LEDs are of red, green and yellow (RGY). The color of the
LEDs is used to show the condition of the UPS. Only one color is shown at one time. The
most urgent condition is always shown. The priority rank is Red,Yellow and Green.
51
UPS OPERATING INSTRUCTIONS
6.2
Control Panel .
Copyright © 2022 Santak Corporation plc. All rights reserved.

Advertisement

Table of Contents
loading

This manual is also suitable for:

Castle 3c3 hd-400Castle 3c3 hd-500Castle 3c3 hd-600

Table of Contents