Huawei LUNA2000-200KWH-2H1 Maintenance Manual page 155

Smart string ess
Hide thumbs Also See for LUNA2000-200KWH-2H1:
Table of Contents

Advertisement

LUNA2000-200KWH-2H1 Smart String ESS
Maintenance Manual
Follow-up Procedure
Step 1 Turn on AC switch 1FCB1 of the CMU adapter power supply.
Step 2 Turn on DC switches 1Q1 and 1Q2 of the ESS.
Step 3 Log in to the SmartLogger WebUI, CMU WebUI, FusionSolar app, or management
system and check that the communication is normal and that no related alarm is
generated.
Step 4 Log in to the SmartLogger WebUI, CMU WebUI, FusionSolar app, or management
system and send a startup command to the rack controller.
Step 5 Check the running status of the system and ensure that the functions are restored.
Step 6 Log in to the CMU WebUI, choose Maintenance > Device Mgmt. > Connect
Device > Auto. Search, and connect the I/O expansion board.
----End
Issue 02 (2023-02-28)
Copyright © Huawei Digital Power Technologies Co., Ltd.
25 Replacing an I/O Expansion Board
149

Advertisement

Table of Contents
loading

This manual is also suitable for:

Luna2000-200kwh-100kw-2h1

Table of Contents