Drainage (Smarty Xv); Connection Of The Air Duct - Salda SMARTY XP Mounting And Installation Instruction

Table of Contents

Advertisement

5.5.5. DRAINAGE (SMARTY XV)

The condensate tube must be filled with water as indicated during the first start-up before every heating season!
DRAINAGE SYSTEM INSTALLATION SMARTY 2X V
It's required to connect condensate drainage system after hanging or placing of air handling unit. Insert condensate draining into AHU. Condensate
draining must be lubricated with a sealant (I-VII) and connected to a condensate removal system.
Remove the sticker on the bottom of the unit, which covers a drainage hole. Then open the unit cover (II) and take out the heat exchanger. Put con-
densate outlet pipe to EPP casing through intended hole (V), use silicon gasket (IV). Place from the bottom side gasket and screw a brass nut on
(VII). Screw the nut by holding the pipe with a hand in order prevent spinning (it's possible to hold with a screwdriver or 1 Euro coin by putting it in
the notch on the pipe). Screw the nut with a wrench (No. 27) until a top part presses in the EPP casing (level with a surface or slightly enters into it).
ATTENTION: Screwing force may not exceed 2 Nm.
Pipe (3) (metal pipe should be connected with G3/8 elbow, plastic pipe – with G3/8 elbow or rubber hose – with strap if the unit is placed on the
legs, in other cases condensate hose can be connected in any direction) should be connected by following order: AHU (1), pipe (2), and drainage
system. Pipes (3) should be bended not less than 3° degrees (1 meter of pipe must be bended 60 mm downwards)! Before turning on AHU (1) the
draining system should be filled up with at least 0.5 l of water (pipe loop (3) must be always filled with water), also check if water reaches sewerage
system! In other case premise can be flooded during AHU operation!
Draining system must be installed in the premise where the temperature is not lower than 1°C. If temperature falls below 0°C the draining system
should be isolated with thermal isolation. The pipe loop 2) not necessarily must be mounted below the AHU (1), but below the AHU (1) level.
NOTE. If the collector is located upstream, install the system with the condensate pump (offered as an accessory).
DRAINAGE SYSTEM INSTALLATION SMARTY 3X V / 4X V
1. Connect the drain couplings (ZPGGM056) part A (G ½ male) to drainage connection into the unit, by turning it clockwise by hand. Do not use
any tools (I-III)!
2. Connect drain couplings part B(G ½ male) to condensate syphon or looped sanitary hose (IV-V).
3. Connect drain couplings A and B parts. Hold back the part A with the key during connection (VI).
5.6.

CONNECTION OF THE AIR DUCT

• The connected air ducts must not be bent and must be fixed separately.
• Make sure that the fans may not be accessed through air duct heads. Otherwise, a protective grid should be installed. You may choose the grid
from the range of products provided on our website https://select.salda.lt.
• Do not reduce the diameter of the piping near the air inlet or exhaust ducts. If you want to reduce the airflow speed in the system, also to reduce
pressure and noise level, you can increase the diameter.
• In order to reduce the level of noise in the air supply system, install silencers (see the chapter on air supply system installation).
SMARTY v2023.2
Figure 5.5.5.1. Drainage system installation (øD=150 mm)
øD
EN |