6 Preparation of commissioning

Fig.72
Connecting the power cable
3
L
N
5.7.6

Cable routing in the control box front part

Fig.73
Cable routing in the control box
front part
6
Preparation of commissioning
6.1

Checklist before commissioning

6.1.1

Filling the installation

42
1. Undo the quarter turn screw.
2. Remove the cover.
3. Connect the power cable to the connector block.
4. Close the cover.
5. Tighten the quarter turn screw.
2
1
AD-3001593-01
Caution
Make sure the cable routing matches the illustration when closing
the control box.
AD-3001768-01
The recommended water pressure is between 1.5 bar and 2.0 bar.
Proceed as follows to fill the installation:
1. Disconnect the boiler from the power supply.
7734324 - v.07 - 21092022