Saving The Commissioning Settings; Settings; Introduction To Parameter Codes - REMEHA Gas 320 Ace Installation And User Manual

High-efficiency standing gas boiler
Hide thumbs Also See for Gas 320 Ace:
Table of Contents

Advertisement

Fig.87
Example filled-in sticker
Adjusted for / Réglée pour /
Ingesteld op / Eingestellt auf
/ Regolato per / Ajustado
para / Ρυθμισμένο για /
Nastawiony na / настроен
для / Reglat pentru /
настроен за / ayarlanmıştır /
Nastavljen za / beállítva/
Nastaveno pro / Asetettu
kaasulle / Justert for/
indstillet til/ ‫: ل طبض‬
G20
Gas
20
mbar
C
(10)3(X)
C
(12)3(X)
7.3.1

Saving the commissioning settings

8

Settings

8.1

Introduction to parameter codes

Fig.88
Code on a HMI T-control
......
........ .......
......
00:12
....................
..... ... ....... .... .. ..... ....
....... .... .. ..... ....
....... ...........
CP010
..... ... ....... ....
..... ... ....... ....
..... ... ....... .... .. ..... ....... .... ..... .......
........ .......
Fig.89
First letter
7734324 - v.07 - 21092022
Parameters / Paramètres /
Parameter / Parametri /
Parámetros / Παράμετροι /
Parametry / Параметры /
Parametrii / Параметри /
Parametreler / Paraméterek
/ Parametrit / Parametere /
Parametre / ‫: تاملعملا‬
DP003 - 3300
GP007 - 3300
GP008 - 2150
GP009 -
AD-3001124-01
.........
.......
...
......
.....
CP010
AD-3001373-02
CP010
AD-3001375-01
10. Fill in the following data on the sticker included, and attach it next to
the data plate on the appliance.
The gas supply pressure;
The flue type, if set to overpressure application;
The parameters modified for the changes mentioned above;
Any fan speed parameters modified for other purposes.
11. Complete the commissioning form, which can be found in annex.
12. Optimise the settings as required for the system and user
preferences.
See
For more information; Settings, page 53 and User instructions,
page 78.
13. Save the commissioning settings on the control panel, so they can be
restored after a reset.
14. Instruct the user in the operation of the system, boiler and controller.
15. Inform the user of the maintenance to be performed.
16. Hand over all manuals to the user.
17. Confirm the commissioning with a signature and a company stamp.
The boiler is now ready for operation.
You can save all current settings on the control panel. These settings can
be restored if necessary, for example after replacement of the control unit.
> Advanced Service Menu > Save as commissioning settings
Use the rotary knob to navigate.
Use the
button to confirm your selection.
1. Press the
button.
2. Select Advanced Service Menu.
3. Select Save as commissioning settings.
4. Select Confirm to save the settings.
When you have saved the commissioning settings, the option Revert
commissioning settings becomes available in the Advanced Service Menu.
The controls platform makes use of an advanced system to categorise
parameters, measurements and counters. Knowing the logic behind these
codes, makes it easier to identify them. The code consists of two letters
and three numbers.
The first letter is the category the code relates to.
A
Appliance: Appliance
C
Circuit: Zone
D
Domestic hot water: Domestic hot water
E
External: External options
G
Gas fired: Gas-fired heat engine
P
Producer: Central heating
Category D codes are appliance controlled only. When the domestic hot
water is controlled by an SCB, it is handled like a circuit, with C-category
codes.