Accessories Provided Depending On The Options Chosen; Analysis Chamber - Pentair E-Box MAESTRO Lite Installation And Operation Manual

Table of Contents

Advertisement

4.3

Accessories provided depending on the options chosen

4.3.1

Analysis chamber

Supplied with the installation kit, it must be installed as close as possible to the Probe Unit box,
and receives the measurement probes provided: RedOx, pH and conductivity.
This chamber contains a flow rate detector incorporated therein.
It is necessary during the installation of the analysis chamber, to comply with the direction in
which the water in it is passing (see Installation of probes [
Analysis chamber kit contents:
• 1 bowl for 3 probes with built-in flow sensor;
• 2 support clamps with a diameter of 50 mm;
th
• 3 m of 6/12
transparent tube;
• 2 DN.15 ¼ turn PVC valves with fittings for the hydraulic tube.
Ref. SB-CU-IMP-062EBLA / A - 11.05.2023
Installation and Operation Guide Version E-Box MAESTRO Lite - Installation
Page 40]).