Commissioning
Make sure that you do not bend the chip card as you insert it into the chip card slot.
6.2.3

Commissioning the PNOZmulti safety system

Procedure:
}
Wire the inputs and outputs on the base unit in accordance with the circuit diagram.
}
Connect the supply voltage:
Please note: The supply voltage for the semiconductor outputs must always be present,
even if you are not using the semiconductor outputs.
6.2.3.1

Load project from chip card

Procedure:
}
Insert the chip card containing the current project into the card slot on the base unit.
}
Switch on the supply voltage. The INFO LED lights when a new or modified project is
present.
}
Load the project by pressing the pushbutton. For the project to be downloaded, the
pushbutton must be held down for between 4 and 8 seconds. Release the pushbutton
while the INFO LED flashes rapidly.
If you hold the pushbutton down for too long, the process will be aborted and the project
will not be downloaded.
Operating Manual PNOZ mm0p-T
1002704-EN-02
NOTICE
Switch off the product before inserting or exchanging the chip card.
Supply voltage for the control system:
Terminal A1: + 24 VDC
Terminal A2: 0 V
Supply voltage for the semiconductor outputs:
24 V terminal: + 24 VDC